LA Metro’s community meetings planned this week for Sepulveda Transit Corridor have been cancelled. According to what Nick Andert is hearing, there is a chance that LA Metro CEO Stephanie Wiggins may be trying to cancel the project.

Nick Andert@nickandert.bsky.social · last yr.

I am hearing some, uh, VERY concerning things about the sepulveda line... trying to get more confirmation but it seems there's a chance Metro (presumably Stephanie Wiggins) is trying to wholly spike the project without releasing the EIR

I am hearing some, uh, VERY concerning things about the sepulveda line... trying to get more confirmation but it seems there's a chance Metro (presumably Stephanie Wiggins) is trying to wholly spike the project without releasing the EIR

March 2025 Metrolink presentation on results of schedule changes. 42.5k rides on Dodger Parade day. Off-peak ridership increased 60% while peak ridership decreased 1%. On-time performance dropped initially but is improving. Ridership is now 60% of Pre-COVID ridership.

BildBildBildBild
@numble.bsky.social · 3y ago

January 2024 Metrolink schedule on proposed schedule revamp. Proposed changes increases service, shifts from commuter-oriented schedule to providing service throughout day, with “pulsed” scheduling to have 4 times amount of transfer opportunities. metrolink.granicus.com/player/clip/...

LA Metro’s camera-based bus lane enforcement program on two routes issued 5,500 tickets (total $1.6m in fines) in the first month, an increase from average of 570 tickets issued per month before camera-based enforcement. laist.com/news/transpo...

Bild

February 2025 status report for LA Metro’s D Line Extension Section 2. 73.5% as of 2/28/25, -3.2% since 1/31/25. Percentage decreased because $72m of extra work was added. Contractor added 7 days to forecast completion, now around mid/late November 2026. libraryarchives.metro.net/DPGTL/Status...

BildBildBildBild
@numble.bsky.social · last yr.

January 2025 status report for LA Metro’s D Line Extension Section 2. 76.7% as of 1/31/25, +0.5% since 12/27/24. No change in forecast completion this month (around early/mid November 2026). libraryarchives.metro.net/DPGTL/Status...

February 2025 status report on LAX Automated People Mover. 91.7% as of 2/22/25, +0.1% since 1/25/25. Percentages are misleading (change orders distort progress). Contractor added 28 days to estimated service date, now 2/9/26 instead of 1/12/26. emma.msrb.org/P11833966-P1...

BildBildBildBild
@numble.bsky.social · last yr.

January 2025 status report on LAX Automated People Mover. 91.7% as of 1/25/25, +0% since 12/28/25. Percentages are misleading (change orders distort progress). Contractor added 2 weeks to estimated service date (now 1/12/26 instead of 12/29/25). emma.msrb.org/P21897139-P2...

January 2025 status report on LAX Automated People Mover. 91.7% as of 1/25/25, +0% since 12/28/25. Percentages are misleading (change orders distort progress). Contractor added 2 weeks to estimated service date (now 1/12/26 instead of 12/29/25). emma.msrb.org/P21897139-P2...

BildBildBildBild
@numble.bsky.social · last yr.

December 2024 status report on LAX Automated People Mover. 91.7% as of 12/27/24, +5.2% since 11/23/24. Percentages are misleading (change orders distort progress). Contractor added 24 days to estimated service date (now 12/29/25 instead of 12/5/25). emma.msrb.org/P11817716-P1...

December 2024 status report on LAX Automated People Mover. 91.7% as of 12/27/24, +5.2% since 11/23/24. Percentages are misleading (change orders distort progress). Contractor added 24 days to estimated service date (now 12/29/25 instead of 12/5/25). emma.msrb.org/P11817716-P1...

BildBildBildBild
@numble.bsky.social · last yr.

November 2024 status report on LAX Automated People Mover. 86.5% as of 11/23/24, +0% since 10/26/24. Percentages are misleading (change orders distort progress). Contractor removed about 5 weeks to estimated service date (now 12/5/25 instead of 1/12/26). emma.msrb.org/P21871677-P2...

November 2024 status report on LAX Automated People Mover. 86.5% as of 11/23/24, +0% since 10/26/24. Percentages are misleading (change orders distort progress). Contractor removed about 5 weeks to estimated service date (now 12/5/25 instead of 1/12/26). emma.msrb.org/P21871677-P2...

BildBildBildBild
@numble.bsky.social · last yr.

October 2024 status report on LAX Automated People Mover. 86.5% as of 10/26/24, +0.1% since 8/28/24. Percentages are misleading (change orders distort progress). Contractor added 4 weeks to estimated service date (now 1/12/26 instead of 12/15/25). emma.msrb.org/P11807187-P1...

October 2024 status report for LA Metro’s D Line Extension Section 2. 74.7% as of 10/26/24, +1.2% since 8/28/24. Contractor added about 3 weeks to forecast completion, now around late November 2026 instead of early November 2026. libraryarchives.metro.net/DPGTL/Status...

BildBildBildBild
@numble.bsky.social · 2y ago

September 2024 status report for LA Metro’s D Line Extension Section 2. 73.4% as of 9/27/24, +1.1% since 8/30/24. Contractor added 2 weeks to estimated completion, now around early November 2026. libraryarchives.metro.net/DPGTL/Status...