CIVAUX 1: Production unavailability - Installed capacity: 1495 MW, remaining capacity: 1345 MW #nuclear https://www.edf.fr/en/the-edf-group/who-we-are/activities/optimisation-and-trading/list-of-outages-and-messages/list-of-outages?mrid=05470-edf-t-00341719
Nuclear Reliability
@reliable-nukes.bsky.social
Live-tweets disruptions at Belgian, Dutch, Swiss, Finnish and French nuclear power plants.
Unplanned, Unavailability of electricity facilities: Production, SE3, Forsmark Block3 #nuclear
umm.nordpoolgroup.com
CATTENOM 1: Production unavailability - Installed capacity: 1300 MW, remaining capacity: 0 MW #nuclear https://www.edf.fr/en/the-edf-group/who-we-are/activities/optimisation-and-trading/list-of-outages-and-messages/list-of-outages?mrid=05470-edf-t-00340024
FLAMANVILLE 2: Production unavailability - Installed capacity: 1330 MW, remaining capacity: 1095 MW #nuclear https://www.edf.fr/en/the-edf-group/who-we-are/activities/optimisation-and-trading/list-of-outages-and-messages/list-of-outages?mrid=05470-edf-t-00341475
FLAMANVILLE 2: Production unavailability - Installed capacity: 1330 MW, remaining capacity: 180 MW #nuclear https://www.edf.fr/en/the-edf-group/who-we-are/activities/optimisation-and-trading/list-of-outages-and-messages/list-of-outages?mrid=05470-edf-t-00341454
PALUEL 1: Production unavailability - Installed capacity: 1330 MW, remaining capacity: 1200 MW #nuclear https://www.edf.fr/en/the-edf-group/who-we-are/activities/optimisation-and-trading/list-of-outages-and-messages/list-of-outages?mrid=05470-edf-t-00334551
GOLFECH 2: Production unavailability - Installed capacity: 1310 MW, remaining capacity: 0 MW #nuclear https://www.edf.fr/en/the-edf-group/who-we-are/activities/optimisation-and-trading/list-of-outages-and-messages/list-of-outages?mrid=05470-edf-t-00340899
PALUEL 1: Production unavailability - Installed capacity: 1330 MW, remaining capacity: 1200 MW #nuclear https://www.edf.fr/en/the-edf-group/who-we-are/activities/optimisation-and-trading/list-of-outages-and-messages/list-of-outages?mrid=05470-edf-t-00334551
Unplanned, Unavailability of electricity facilities: Production, BE, TIHANGE 3 #nuclear
umm.nordpoolgroup.com
Unplanned, Unavailability of electricity facilities: Production, BE, TIHANGE 3 #nuclear
umm.nordpoolgroup.com
Romania left without nuclear power after Cernavodă reactors shut down: Romania’s Cernavodă nuclear power plant shut down both reactors on the evening of November 9, shortly after Unit 1 resumed electricity… Bne IntelliNews #Romania #EnergieNucleară #Cernavodă #SecuritateEnergetică #ReactoareNucleare
Romania left without nuclear power after Cernavodă reactors shut down
Romania’s Cernavodă nuclear power plant shut down both reactors on the evening of November 9, shortly after Unit 1 resumed electricity generation and preparations were under way to restart Unit 2.
dlvr.it
Unplanned, Unavailability of electricity facilities: Production, BE, TIHANGE 3 #nuclear
umm.nordpoolgroup.com
GOLFECH 2: Production unavailability - Installed capacity: 1310 MW, remaining capacity: 300 MW #nuclear https://www.edf.fr/en/the-edf-group/who-we-are/activities/optimisation-and-trading/list-of-outages-and-messages/list-of-outages?mrid=05470-edf-t-00340899
CIVAUX 1: Production unavailability - Installed capacity: 1495 MW, remaining capacity: 1350 MW #nuclear https://www.edf.fr/en/the-edf-group/who-we-are/activities/optimisation-and-trading/list-of-outages-and-messages/list-of-outages?mrid=05470-edf-t-00340812
Unplanned, Unavailability of electricity facilities: Production, BE, TIHANGE 3 #nuclear
umm.nordpoolgroup.com
Unplanned, Unavailability of electricity facilities: Production, BE, TIHANGE 3 #nuclear
umm.nordpoolgroup.com
CHOOZ 2: Production unavailability - Installed capacity: 1500 MW, remaining capacity: 0 MW #nuclear https://www.edf.fr/en/the-edf-group/who-we-are/activities/optimisation-and-trading/list-of-outages-and-messages/list-of-outages?mrid=05470-edf-t-00338765
ST LAURENT 1: Production unavailability - Installed capacity: 915 MW, remaining capacity: 45 MW #nuclear https://www.edf.fr/en/the-edf-group/who-we-are/activities/optimisation-and-trading/list-of-outages-and-messages/list-of-outages?mrid=05470-edf-t-00340612
CHOOZ 2: Production unavailability - Installed capacity: 1500 MW, remaining capacity: 0 MW #nuclear https://www.edf.fr/en/the-edf-group/who-we-are/activities/optimisation-and-trading/list-of-outages-and-messages/list-of-outages?mrid=05470-edf-t-00338765
Dukovany B3 (CZ) – Outage, 08 Nov 04:00 → 08 Nov 04:15 (0.3h), 451 MW not available | Failure #nuclear
CHOOZ 2: Production unavailability - Installed capacity: 1500 MW, remaining capacity: 0 MW #nuclear https://www.edf.fr/en/the-edf-group/who-we-are/activities/optimisation-and-trading/list-of-outages-and-messages/list-of-outages?mrid=05470-edf-t-00338765
CATTENOM 1: Production unavailability - Installed capacity: 1300 MW, remaining capacity: 0 MW #nuclear https://www.edf.fr/en/the-edf-group/who-we-are/activities/optimisation-and-trading/list-of-outages-and-messages/list-of-outages?mrid=05470-edf-t-00340024
PALUEL 4: Production unavailability - Installed capacity: 1330 MW, remaining capacity: 0 MW #nuclear https://www.edf.fr/en/the-edf-group/who-we-are/activities/optimisation-and-trading/list-of-outages-and-messages/list-of-outages?mrid=05470-edf-t-00339928
CHOOZ 2: Production unavailability - Installed capacity: 1500 MW, remaining capacity: 0 MW #nuclear https://www.edf.fr/en/the-edf-group/who-we-are/activities/optimisation-and-trading/list-of-outages-and-messages/list-of-outages?mrid=05470-edf-t-00338765
CHINON 1: Production unavailability - Installed capacity: 905 MW, remaining capacity: 280 MW #nuclear https://www.edf.fr/en/the-edf-group/who-we-are/activities/optimisation-and-trading/list-of-outages-and-messages/list-of-outages?mrid=05470-edf-t-00339769
PENLY 1: Production unavailability - Installed capacity: 1330 MW, remaining capacity: 310 MW #nuclear https://www.edf.fr/en/the-edf-group/who-we-are/activities/optimisation-and-trading/list-of-outages-and-messages/list-of-outages?mrid=05470-edf-t-00339696
ST LAURENT 2: Production unavailability - Installed capacity: 915 MW, remaining capacity: 370 MW #nuclear https://www.edf.fr/en/the-edf-group/who-we-are/activities/optimisation-and-trading/list-of-outages-and-messages/list-of-outages?mrid=05470-edf-t-00339172
DAMPIERRE 3: Production unavailability - Installed capacity: 890 MW, remaining capacity: 180 MW #nuclear https://www.edf.fr/en/the-edf-group/who-we-are/activities/optimisation-and-trading/list-of-outages-and-messages/list-of-outages?mrid=05470-edf-t-00339711
PENLY 1: Production unavailability - Installed capacity: 1330 MW, remaining capacity: 310 MW #nuclear https://www.edf.fr/en/the-edf-group/who-we-are/activities/optimisation-and-trading/list-of-outages-and-messages/list-of-outages?mrid=05470-edf-t-00339696
ST LAURENT 2: Production unavailability - Installed capacity: 915 MW, remaining capacity: 370 MW #nuclear https://www.edf.fr/en/the-edf-group/who-we-are/activities/optimisation-and-trading/list-of-outages-and-messages/list-of-outages?mrid=05470-edf-t-00339172